18 weeks
Project Duration
7
Buildings Accessed
4
Trades Served
Mixed
Scaffold Type
Scaffolding across multiple heritage and modern buildings on the MAGS campus presented a complex logistical challenge. Access requirements spanned re-roofing of the original 1930s stone buildings, exterior refurbishment of modern teaching blocks, and installation of new cladding to the performing arts centre.
Working around an occupied school with over 3,000 students required meticulous planning and strict site management protocols. SL Scaffolds implemented daily exclusion zone procedures and worked closely with school management to schedule noisy or disruptive works during non-teaching periods.
Key Highlights
Heritage and modern building access across a live school campus
Strict daily exclusion zone and noise management protocols
Works sequenced around school timetable with zero student disruption
Heritage scaffolding techniques used on 1930s stone buildings